Service Interruptions

Here you will find a current list of ongoing and upcoming service interruptions across the campus.

Service Interruptions & Outages

 

Date

Location and

Work Area

Impact for Building Residents

Project Manager

9/24-10/9

East Campus

Please be advised that Long Building Technologies will be onsite in East Campus from September 24 through October 9, between 9:00 a.m. and 5:00 p.m., to install new controllers on the heat pumps.

Controllers will be installed one heat pump at a time, with each unit tested to ensure full functionality before work proceeds to the next heat pump.

During the installation, occupants may experience intermittent loss of heating and/or cooling as individual heat pumps are taken offline.

We apologize for any inconvenience and appreciate your patience while this work is completed.

 

Karl Sanchez

Ext 6578

 

 

 

 

Updated 9/29

 

Date

Location and

Work Area

Impact for Building Residents

Project Manager

9/26

9/28-10/2

Olin Hall

Please be advised that, as part of the planning and design process for the New Science Building Project, a geotechnical survey crew will be conducting soil test borings around Olin Hall to evaluate subsurface conditions.

Work Schedule:

  • Saturday, September 26: All-day drilling operations
  • Monday, September 28–Friday, October 2: Daily work beginning after 1:00 p.m.

Test borings will be conducted on the east, west, and south sides of Olin Hall. Survey and drilling crews will access the work areas from Armstrong Lot, areas north of Barnes Science Center, and Nevada Avenue.

Community members may notice drilling equipment and support vehicles, survey stakes and utility markings, and temporary activity around the designated work areas.

We appreciate your patience and cooperation while this work is underway.

 

Kenny Rankin

Ext 6570

 

 

 

 

Posted 9/22

 

Date

Location and

Work Area

Impact for Building Residents

Project Manager

10/5-10/13

1002 Weber St (Kappa Sigma)

 

1008 Weber St

 

916 Weber St

 

1107 N Cascade (Mierow)

 

1109 N Cascade (Dern)

 

1130 N Cascade (Morreale)

 

922 N Weber St

Please be advised that backflow installations will be taking place at the following locations on the dates listed below:

  • Monday, October 5: 1002 Weber St (Kappa Sigma)

 

  • Tuesday, October 6: 1008 Weber St

 

  • Wednesday, October 7: 916 Weber St

 

  • Thursday, October 8: 1107 N. Cascade Ave(Mierow)

 

  • Friday, October 9: 1109 N. Cascade Ave (Dern)

 

  • Monday, October 12: 1130 N. Cascade Ave (Morreale)

 

  • Tuesday, October 13: 922 N. Weber St

Water service will be interrupted from 9:30 a.m. to 4:30 p.m. each day at the respective locations while the installations are completed.

 

Please plan accordingly and thank you for your patience and understanding during this work.

      

 

Marcus Moreno

Ext 6915

 

 

 

 

Posted 10/2

  

Date

Location and

Work Area

Impact for Building Residents

Project Manager

Ongoing

Spencer Center

       ** UPDATE **

The Breakroom in the Spencer Center is now accessible and back in service.

Ameri-Dri is awaiting flooring materials to complete the remaining remediation work in the breakroom.

We appreciate your patience and understanding as we work to complete the remaining repairs. We apologize for any inconvenience.

        

 

Luke Scott

Ext 6678

 

 

 

 

Updated 10/1

 

Date

Location and Work Area

Impact for

Building Residents

Project Manager

 

 

Cascade Ave by Armstrong

     *****ON HOLD*****

Heating system repairs will replace the underground central heating system piping between Armstrong and Worner.

Excavation will take place on the north side of Armstrong along the sidewalk  of Cascade Ave.

Please expect construction equipment, concrete trucks, noise, and general construction activity in the area during this work.

 

Mike Brubaker

Ext 7115

 

 

 

 

Updated 8/12

 

Date

Location and

Work Area

Impact for Building Residents

Project Manager

9/25-10/9

Advising Hub

1014 N Weber

Please be advised that the front entrance to the Advising Hub at 1014 N. Weber will be inaccessible from September 25 through October 9 while the CC Carpentry Shop removes and replaces the front porch stairs and handrail.

During this work, occupants and visitors may experience noise and increased foot traffic in the area. The work area has been sectioned off with caution tape.

Please use the back entrance on the west side of the building during this time.

We apologize for any inconvenience and appreciate your patience while this work is completed.

 

Alex Guido

Ext 6977

 

 

 

 

Posted 9/25

   

Date

Location and Work Area

Impact for

Building Residents

Project Manager

Ongoing

East Campus Resident Buildings

We would like to provide an update on the ongoing efforts to restore full functionality to the East Campus heating and cooling system.

At this time, all systems other than the heating and cooling system have been restored and are fully functional. Our teams are continuing to work diligently to restore full functionality to the heating and cooling system as quickly as possible.

We appreciate your patience and understanding as we work to complete these repairs. Additional updates will be shared as more information becomes available.

If you have any concerns or questions, please don’t hesitate to reach out.

 

Luke Scott

Ext 6678

 

 

 

Updated 6/5

 

Date

Location and Work Area

Impact for

Building Residents

Project Manager

Ongoing

Armstrong Hall

The heating system in Armstrong Hall is still out of service due to emergency repairs to the building’s hot water system.

Repairs are ongoing, and full heating service has not yet been restored.

Please contact Facilities with any questions or concerns.

Thank you for your patience and understanding.

Mike Brubaker

Ext 7115

 

 

 

Updated 5/5

  

 

Report an issue - Last updated: 10/02/2026