"The Plan" and Current Status

An overall look at the upgrade process and where we're currently at. You'll see more detailed information in the form of email messages and fliers about these events.

TIP: Press CTRL+F (the "Find" command) and type the name of your building to find it more quickly in the list below.

Wireless Network (July 1, 2006 -- August 30, 2007)
Intensive vendor selection process with WTC consulting COMPLETE! (01/15/07)
Final choice of wireless vendor (Aruba) COMPLETE! (03/14/07)
Conduct site survey to determine appropriate access point coverage COMPLETE! (04/25/07)
Final Design and technical review process COMPLETE! (05/25/07)
Sign Final contract with Aruba COMPLETE! (06/19/07)
Receive test equipment and build the process of connecting, including documentation and any scripting for automating as much of it as possible. COMPLETE! (08/19/07)
Install new wired ports in which the new Access Points will be connected COMPLETE! (08/07/07)
Phase 1 Access Point Installations (Armstrong, Slocum, Worner, Packard) COMPLETE! (07/16/07)
Phase 2 Access Point Installations (Spencer, Bemis) COMPLETE! (07/18/07)
Phase 3 Access Point Installations (McGregor, Morreale, Mullet, Cossitt, Cutler, Montgomery, Ticknor, Haskell, Max Kade, Field Maintenance Shop, Heating Plant, Arthur, Lennox, Shove, CC Inn, Art & Drama, Central Services, Tutt Science) COMPLETE! (07/29/07)
Phase 4 Access Point Installations (Weber buildings - 1014, 1016, 1018, 1024, 1028, 1116, Sororities & Fraternaties, Interfaith, KRCC, Little CC, Outdoor, Tutt Library COMPLETE! (08/07/07)
Migration (new APs turned on and tested, not cutover yet) of Mathias, Palmer, Slocum, Worner, Loomis, Bemis, Spencer, Packard, Antero.
COMPLETE! (08/13/07)
Migration (new APs turned on and tested, not cutover yet) of all remaining buildings.
COMPLETE! (08/15/07)
Testing to make sure coverage is excellent and everything works
COMPLETE! (02/31/08)
Announce new method of connecting to wireless to the campus - users will be able to connect either the new way or the old way (LEAP)
COMPLETE! (08/22/07)
Declare final cutover and turn off all old APs for good
COMPLETE! (10/22/07)
Disable LEAP authentication protocol
Summer, 2008
Finalize any outstanding issues and declare the project finished!
Currently Underway
Wired Network (July 1, 2006 -- June 22, 2007) - COMPLETE!
Intensive vendor selection process with WTC consultants COMPLETE! (12/20/06)
Sign final contract with Foundry Networks COMPLETE! (01/12/07)
Launch website to be hub of communication regarding network upgrade COMPLETE! (02/11/07)
Install new network hardware in Bemis, Blanca, El Diente, JLK, McGregor COMPLETE! (02/13/07)
Install new network hardware in Edith Gaylord, Elbert, Haskell, Loomis COMPLETE! (02/15/07)
Install new network hardware in core areas (Armstrong and Barnes) COMPLETE! (02/21/07)
Install new hardware in distribution nodes (Loomis, Worner, etc.) COMPLETE! (02/22/07)
Install new network hardware in various buildings around campus COMPLETE! (03/13/07)
Configure new switches; design VLAN structures COMPLETE! (03/14/07)
Downtime - Cutover in Children's Center, Lennox, Jackson, & Dean Edmonds' house COMPLETE! (03/15/07)
Downtime - Internal wiring in Bemis, Loomis, Slocum, & Mathias COMPLETE! (03/16/07)
Downtime - Cutover in North Weber buildings COMPLETE! (03/16/07)
Downtime - Cutover in Palmer, Tutt Library, Barnes, Olin, Tutt Science, Mierow, Mathias, Arthur, Dern, Gill, & ID House COMPLETE! (03/17/07)
Downtime - Cutover in Worner Campus Center COMPLETE! (03/19/07)
Downtime - Cutover in Packard, Cossitt, Honnen Ice Rink, & Heating Plant COMPLETE! (03/19/07)
Downtime - Cutover in Cutler COMPLETE! (03/19/07)
Downtime - Cutover in Loomis, McGregor, Antero, El Diente, John Lord Knight, & 1210 N. Wood Ave. COMPLETE! (03/20/07)
Downtime - Cutover in Facilities Services, Boettcher Health Center, Haskell, Montgomery, Windom, Hamlin, Faculty Housing, Field Maintenance Shop, & Grounds Shop COMPLETE! (03/20/07)
Downtime - Cutover in Ticknor COMPLETE! (03/20/07)
Downtime - Cutover in Bemis, El Pomar Sports Center, Tutt Alumni House, Blanca, Elbert, Max Kade, Morreale, Mullett, President's House, & Washburn Press Box COMPLETE! (03/21/07)
Downtime - Cutover in Edith Gaylord Apartments (Campus Security) COMPLETE! (03/21/07)
Downtime - Cutover in Slocum, Shove Chapel, Central Services & Art & Drama Workshop COMPLETE! (03/22/07)
Downtime - Cutover in Armstrong & Spencer COMPLETE! (03/22/07)
Downtime - Finish cutovers in Barnes, Tutt Science, and Tutt Library COMPLETE! (03/23/07)
Downtime - Cutover in Sodexho Office, Synergy House, Interfaith House, and fraternities / sororities COMPLETE! (04/18/07)
Migrate non-computer network devices to new network (e.g., printers, copiers, door access, security cameras, HVAC building controllers, cash registers, etc.) COMPLETE! (04/20/07)
Downtime - Server cutover (e.g., email, H:\ & I:\ drives, print servers, etc.) COMPLETE! (04/20/07)
40-day "Acceptance Period" before the cutover is considered complete COMPLETE! (06/13/07)
Finalize any outstanding issues and declare the project finished! COMPLETE! (06/22/07)

This page last revised on August 24, 2007.